Construction subcontract


Scope of Works

The Scope is to be as detailed on the drawings provided by the Employer and priced within the lump sum stated in 2.1 below.


1.0 Programme

1.1 All Contract works contained within current programme __ and any additions thereto shall take priority over the =====.

1.2 =====shall not commence until the completion and formal Taking Over of the by the Employer of

1.3 Time for Completion date for the will be extended to the date of the completion of the =====.

1.4 Individual sections shall be Taken Over individually by the Employer upon completion.  Defects Liability periods shall commence from the date of the individual Take Over certificates.

1.5 Delay Damages will apply to the =====only. The date for the application of Delay Damages to shall be amended to the date in 1.3 above.  

2.0 Payment Conditions

2.1 Employer will nominate the Subcontractor who will subcontract on fixed lump sum on (with amendments see 3.3) standard nominated subcontractor conditions included within the Contract Particular Conditions. Milestones for payment purposes to be agreed.

2.2 Contractor will be entitled to an attendance fee of ……………% which will be applied to the final account sum of the subcontract works.

2.4 Employer to make arrangements with =====to ensure all works and payments are covered within the scope of the =====loan agreement. Employer to provide written evidence to this effect.

2.5 Conditions for the Performance Guarantee will not be extended for the =====, but will apply to the original Contract Works only.

3.0 Special Conditions

3.1 Time for Completion has been amended as per 1.3 above, however the Employer’s liabilities have not been concluded. Employer accepts to instruct the Engineer to continue to evaluate all present and future variations and claims by the Contractor in accordance with the Contract, in order to properly assess the Employer’s liabilities.

3.2 Employer to indemnify the Contractor for any damage or defect to the Contract works which are caused by the construction of the =====.     

3.3 Standard nominated subcontract conditions are to be amended in order for the subcontractor to be directly responsible to the Engineer for a) Safety, b) Quality Issues, c) Testing, d) Documentation, e) Environmental issues, f) Insurance of the works, and all issues pursuant to the Take Over of the works by the Employer. 

4.0 Exclusions

The following activities are specifically excluded from the cost and programme of works:

4.1 Liaison and coordination with any Bulgarian Authority or body who is, or maybe affected by the works.

4.2 Liaison and coordination with the public or any business or enterprise who is, or maybe affected by the works.

4.3 Provision of any new external services required to the new building

4.4 Any utility diversions required in order for the =====to be converted.

4.5 Any support or temporary support to any structure (including utilities) which may be affected by the =====. 

4.6 Completion of any investigation works.

4.7 Any amendments required to the layout of beyond the =====, including but not limited to; road layout, lighting, drainage, line marking, street furniture, pedestrian walkways etc.

4.8 Hard and soft landscaping works; including the removal of any existing .

4.9 Any temporary or permanent noise reduction measures required in order to meet requirements.

4.10 Any additional works required in connection with geological conditions which are not included within the Employers survey. 